22000
m³ of Material Moved
3000
m³ of Rock Processed
ST9
Location
Challenge
The extension to the Northern end of the existing substation was to be cut in to an existing bank with restricted access and egress.
If the material was to be moved through the live substation it would have impacted operations and added months to the operation. The project included: –
- Temporary access
- Footpath diversion
- Site clearance
- Earthworks
- Material processing
- Temporary works
- Validation
There was also rock at relatively shallow depths.
Solution
Negotiation with adjacent landowners and temporary protection measures were introduced to allow us to remove the surplus material without the need to traffic through the live site.
Due to the nature of the road and weight restrictions, we utilised agricultural tractors and trailers to remove the materials opposed to articulated dumptrucks.
We were able to process enough of the rock to provide the backfill material for the new retaining walls which saved on both import and export of materials.
Project gallery
At ACS Midlands we have many capabilities. Get in touch for more information on this project or to discuss your requirements.
Project
Retail Unit, Thornton Cleveleys
The Client required a retail unit to utilise a plot at the entrance to a new housing development in Thronton Cleveleys, near Blackpool.
Project
Phases 4E, 4G and Eastern Lakes
This 600-acre former steelworks was being transformed into a mixed-use development with housing. We were asked to provide earthworks solutions across a complex site with challenging ground conditions.
Project
Local Centre Buildings, Wantage
Design adn construction of 3 commercial retail units to shell only stage, to achieve BREEAM Very Good standard
Project
Amphitheatre, BCFC
Design and Construct sections 1 & 2 of the Wantage Eastern Link Road including connections to existing highways.