Project

Cellarhead Substation

22000

m³ of Material Moved

3000

m³ of Rock Processed

ST9

Location

Challenge

The extension to the Northern end of the existing substation was to be cut in to an existing bank with restricted access and egress.

If the material was to be moved through the live substation it would have impacted operations and added months to the operation. The project included: –

  • Temporary access
  • Footpath diversion
  • Site clearance
  • Earthworks
  • Material processing
  • Temporary works
  • Validation

There was also rock at relatively shallow depths.

Solution

Negotiation with adjacent landowners and temporary protection measures were introduced to allow us to remove the surplus material without the need to traffic through the live site.

Due to the nature of the road and weight restrictions, we utilised agricultural tractors and trailers to remove the materials opposed to articulated dumptrucks.

We were able to process enough of the rock to provide the backfill material for the new retaining walls which saved on both import and export of materials.

At ACS Midlands we have many capabilities. Get in touch for more information on this project or to discuss your requirements.

Project

Club Shop, BCFC

The renovation of the club shop to meet the requirements of Nike retail standards. This included strip out, forming new shop frontage facilitated by major alterations to the existing steel frame, new internal walls, M&E, HVAC, shopfitting, flooring and decoration.

Project

Pavilion Building, Wantage

The client required a sports pavilion to utilise a plot at the centre of a large new build housing development in Wantage, near Oxford.

Project

Phases 4E, 4G and Eastern Lakes

This 600-acre former steelworks was being transformed into a mixed-use development with housing. We were asked to provide earthworks solutions across a complex site with challenging ground conditions.